sthaambika145
sthaambika145 sthaambika145
  • 02-08-2021
  • Mathematics
contestada

15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

2. What number would you divide by to calculate the mean of 3, 4, 5, and 6? a. 6 b. 3 c. 5 d. 4
If you throw exactly one head in three tosses of a coin you win $28. if not, you pay me $12. Step 2 of 2: If you played this game 756 times how much would you e
how water pollution affect human health
Express the decimal as a percent. 1.276 60 points.
can someone tell me the answer
What is the perimeter of a square with a side length of 7 cm? A. 7 cm B. 14 cm C. 21 cm D. 28 cm
Quarter 3 semester 2 midterm writing listen to the audio and summarize the main points.your response must contain at least 5 detailed and complete sentences in
The sum or difference of p and q is the of the x-term in the trinomial.​a. ss. www. coefficients
What is the primary focus of US national security policy? O invading hostile countries O reaching trade agreements O protecting citizens and the nation O buildi
Historically, hierarchical scale has been used by artists to communicate power or rank in social and religious contexts, but identifying importance using scale