Jin schedules 496 hours for a project. He plans to work 8 hours each day. How many days will it take to complete the project?​

Respuesta :

penguinlife90 penguinlife90
  • 01-12-2021

Answer:

62 days

Step-by-step explanation:

496/8 = 62

Answer Link
clickykeyboardasmr
clickykeyboardasmr clickykeyboardasmr
  • 01-12-2021

496/8=62

Hope this helps!

Answer Link

Otras preguntas

A wheelbarrow can be used to help lift a load, such as a pile of dirt, and then push the load across a distance. Which simple machines make up a wheelbarrow? a
What would be the correct sentence? nous / s'asseoir
How did railroad companies profit from the building of the transcontinental railroad? A. by selling railroad lines back to the federal government at a profit B.
What is the equation of a line that is parallel to the line x=-2and passes through the point (-5, 4)?
i'm not quite sure how to do this
Alg. 1 - Essential Questions - Module 3 - Lesson 03.07 - Horizontal and Vertical Lines: How do you graph horizontal and vertical lines?
i tried to do these they just aren't cliqueing with me :/
The theme park company is building a scale model of the killer whale stadium main show tank for an investor's presentation. Each dimension will be made 6 times
Which of the following government agencies determines how much money is in the economy?
Which of the following points lies on the circle whose center is at the origin and whose radius is 13? (-5, 12) (, ) (6, -7)