Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

What were the contributions of the Harappan civilization?
What's 5 divided by x squared explain
find the sum. write each mixed number in simplest form 4 7/8 + 5 1/4
What all the multiples of 81?
What all the multiples of 81?
a lunch bill including tax, is divided among you and 5 friends. everyone pays less than $8.75. write and solve an inequality that describes the total amount of
find the sum. write each mixed number in simplest form 4 7/8 + 5 1/4
A blue rope is 3 times the length as a red rope. A green rope is 5 times as log as the blue rope of the total length of all 3 ropes equals 508.25m what is the l
What is the creepiest sounding scale? What scale would u use for writing creepy music in other words
find the sum. write each mixed number in simplest form 4 7/8 + 5 1/4